Effective Communication as a Strategic Element for Dispute Avoidance in Gulf Cooperation Council Construction Projects

Authors

  • Ali Al-Khalifa

Keywords:

communication management, countdown clock artefact, design science research, dispute avoidance/claim avoidance committee, dispute avoidance, early-warning systems, escalation mechanism, Gulf Cooperation Council construction projects, key result indicators, proactive communication, proactive contracting, structured communication

Abstract

Effective communication is the first line of defence against Gulf Cooperation Council (GCC) construction disputes, where escalating compressed programmes and multicultural teams risk misunderstandings. The current study elaborates on four communication-centric artefacts—dispute avoidance/claim avoidance committee (DACA), countdown clock, aligning project managers’ key result indicators (KRIs), and escalation mechanism—to improve communication in this field. This GCC construction field study is based on the five-stage design science research cycle comprising exploration, development, implementation, evaluation, and conclusion. The executive-level DACA meets routinely or ad hoc when a formally escalated issue demands chief executive officer-level attention. A project-wide countdown clock mirrored to cloud dashboards and daily briefings keeps on-site and remote actors aware of milestone pressures. Alignment of project managers’ KRIs redirects attention from historical cost–time metrics to forward-looking communication health, whereas a tiered escalation mechanism provides a transparent, time-bound pathway for matters exceeding the DACA’s remit. Qualitative evidence shows that integrated use of these artefacts shortens issue-resolution lead times and curtails the escalation of incipient claims. These tools can convert latent dispute triggers into managed risks by feeding their outputs directly into the project risk register. This study fills GCC?specific evidence gaps on proactive, communication?driven dispute avoidance tools.

References

[1]. M. Aladwani, S. Mollasalehi, and A. Fleming. “A study of root causes of delays in the public-sector construction projects in Kuwait.” 2019.

[2]. A. Al Khalifa. “Proactive conflict detection and management in the construction industry: Integrating multi-faceted approaches for dispute prevention.” Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 2025.

[3]. M.A.U Abdul-Malak and M.T. El-Saadi. “Proactive contract design for dispute avoidance in GCC construction.” Journal of Construction Engineering and Management, vol. 126, no. 1, pp. 33-41, 2000.

[4]. K. Al-Reshaid, N. Kartam, N. Tewari, and H. Al-Bader. “A project control process in pre‐construction phases: focus on effective methodology.” Engineering, Construction and Architectural Management, vol. 12, no. 4, pp. 351-372, 2005.

[5]. Arcadis. Global Construction Disputes Report 2024: The Search for Higher Ground. The Netherlands: Arcadis N.V., 2024.

[6]. H.M. Mehany, E. Elbeltagi, and Y. Helmy. “Framework for early dispute avoidance in Middle-East construction projects.” International Journal of Construction Management, vol. 18, no. 6, pp. 494-509, 2018.

[7]. A.P.C. Chan, D. Scott, and A.P.L. Chan. “Factors affecting the success of a construction project.” Journal of Construction Engineering and Management, vol. 130, no. 1, pp. 153-155, 2004.

[8]. Project Management Institute. A guide to the project management body of knowledge (PMBOK guide), 6th ed., Newtown Square, PA: PMI, 2017.

[9]. S.O. Cheung, T.W. Yiu, and S.F. Yeung. “A study of construction dispute negotiation strategy.” Journal of Construction Engineering and Management, vol. 132, no. 10, pp. 1053-1062, 2006.

[10]. S. Mitkus and T. Mitkus. “Causes of conflicts in a construction industry: a communicational approach.” Procedia – Social and Behavioral Sciences, vol. 110, pp. 777-786, 2014.

[11]. M. Loosemore and W. Hughes. “Avoiding communication pitfalls during construction disputes.” Construction Management and Economics, vol. 35, no. 3, pp. 179-190, 2017.

[12]. P.E.D. Love, Z. Irani, and D.J. Edwards. “A taxonomy of organisational structures.” Construction Management and Economics, vol. 21, no. 1, pp. 11-20, 2003.

[13]. M. Norouzi, T. Yiu, M. Manuel, and M. Sharif. “Managing communication in architectural design: technical versus social issues.” Architectural Engineering and Design Management, vol. 11, no. 4, pp. 271-287, 2015.

[14]. L. Bourne. Stakeholder relationship management: a maturity model for organisational implementation, 2nd ed., Abingdon, UK: Routledge, 2016.

[15]. E. Safapour, S. Kermanshachi, and S. Kamalirad. “Development of effective communication networks in construction projects using structural-equation modelling.” Computing in Civil Engineering 2019: Data, Sensing and Analytics, pp. 513-521, 2019.

[16]. S.O. Cheung and H.C.H. Suen. “A multi-attribute utility model for dispute-resolution strategy selection.” Construction Management and Economics, vol. 20, no. 7, pp. 557-568, 2002.

[17]. P.E.D. Love, P.R. Davis, S.O Cheung, and Z. Irani. “Causal discovery in contractual disputes: a data-mining approach.” Journal of Construction Engineering and Management, vol. 137, no. 4, pp. 244-252, 2011.

[18]. S.T. Al-Sedairy. “A cultural model for communication patterns in construction projects.” Engineering, Construction and Architectural Management, vol. 8, no. 5-6, pp. 412-422, 2001.

[19]. O. Ikechukwu, C.E. Okechukwu, and R.E. Ikechukwu. “Communication management practice for construction project success.” Journal of Engineering, Design and Technology, vol. 15, no. 3, pp. 324-334, 2017.

[20]. Y. Gamil and I. Abd Rahman. “The impact of communication effectiveness on construction project success.” Journal of Construction in Developing Countries, vol. 26, no. 1, 2021.

[21]. S. Assaf and S. Al-Hejji. “Causes of delay in large construction projects.” International Journal of Project Management, vol. 24, no. 4, pp. 349-357, 2006.

[22]. A.H. Al-Momani. “Construction delay: a quantitative analysis.” International Journal of Project Management, vol. 18, no. 1, pp. 51-59, 2000.

[23]. E.T. Hall. Beyond culture. New York, NY: Anchor Press/Doubleday, 1976.

[24]. G. Hofstede. Culture’s consequences, 2nd ed., Thousand Oaks, CA: Sage, 2001.

[25]. E.W. Larson. “Partnering on construction projects: a study of the formation and strategic benefits.” International Journal of Project Management, vol. 15, no. 2, pp. 91-98, 1997.

[26]. W. Alaloul, M. S. Liew, and N. A. W. A. Zawawi. “Communication, coordination and cooperation in construction projects: business environment and human behaviours,” IOP Conference Series: Materials Science and Engineering, vol. 291, no. 1, p. 012003, 2017.

[27]. R.L. Daft and R.H. Lengel. “Organizational information requirements, media richness and structural design.” Management Science, vol. 32, no. 5, pp. 554-571, 1986.

[28]. D.C. Barnlund. “A transactional model of communication,” in Foundations of communication theory, K.K. Sereno and C.D. Mortensen, Eds. New York: Harper & Row, 1970, pp. 43-61.

[29]. A.M. Al-Hammad. “Early-warning mechanisms for conflict containment in GCC infrastructure projects.” International Journal of Project Management, vol. 41, no. 8, p. 102566, 2023.

[30]. S.O. Cheung, T.W. Yiu, and S.F. Yeung. “Management of construction disputes: role of communication.” Journal of Construction Engineering and Management, vol. 144, no. 2, p. 04017103, 2018.

[31]. B. G. Zulch. “Communication: The foundation of project management.” Procedia Technology, vol. 16, pp. 1000-1009, 2014.

[32]. R.E. Freeman. Strategic management: a stakeholder approach. Boston, MA: Pitman, 1984.

[33]. M. Latham. Constructing the team. London: HMSO, 1994.

[34]. UK Department of Trade and Industry. Rethinking construction: the report of the construction task force. DTI, London, 1998.

[35]. K. Essex. “Partnering agreements for early dispute avoidance.” Proceedings of the ICE – Civil Engineering, vol. 114, no. 2, pp. 65-71, 1996.

[36]. C. Glagola and Sheedy. “Partnering on defense contracts.” Journal of Construction Engineering and Management, vol. 128, no. 2, 2002.

[37]. A. Gamage. “Importance of effective communication to minimize disputes in construction projects.” Scholars Journal of Engineering and Technology, vol. 10, no. 7, pp. 128-140, 2022.

[38]. International Organization for Standardization, ISO 44001:2017 – Collaborative business-relationship management systems: requirements and framework. Geneva, Switzerland: ISO, 2017.

[39]. P. Hietanen-Kunwald and H. Haapio. “Proactive contracting for sustainable construction projects,” International Journal of Law in the Built Environment, vol. 13, no. 2, pp. 165–182, 2021.

[40]. N. Jaffar, A. H. A. Tharim, and M. N. Shuib. “Factors of conflict in construction industry: a literature review,” Procedia Engineering, vol. 20, pp. 193–202, 2011.

[41]. G. F. Jergeas and F. T. Hartman. “Contractors’ construction-claims avoidance,” Journal of Construction Engineering and Management, vol. 120, no. 3, pp. 553–560, 1994.

[42]. P. E. D. Love, J. Smith, and J. Georgiou. “Building disputes and the use of conflict-management mechanisms in the Australian construction industry,” Engineering, Construction and Architectural Management, vol. 17, no. 2, pp. 114–134, 2010.

[43]. G. Soni, V. Rai, and R. Rawal. “Communication bottlenecks as a cause of construction disputes: an Indian contractor’s perspective,” International Journal of Construction Management, vol. 17, no. 4, pp. 268–284, 2017.

[44]. G. M. Winch. Managing construction projects: an information-processing approach, 2nd ed. Oxford, UK: Wiley-Blackwell, 2010.

Downloads

Published

2025-11-01

Issue

Section

Articles

How to Cite

Ali Al-Khalifa. (2025). Effective Communication as a Strategic Element for Dispute Avoidance in Gulf Cooperation Council Construction Projects. International Journal of Sciences: Basic and Applied Research (IJSBAR), 78(1), 283-305. https://www.gssrr.org/JournalOfBasicAndApplied/article/view/17620